Port Augusta’s Central Oval Turf Update

grass 2

Port Augusta’s Central Oval is currently being upgraded due to grant funding of close to $500,000 provided through the Office for Recreation, Sport & Racing’s Grassroots Football, Netball and Cricket Fund.

Irrigation and the growing medium have been put in place and finalised, with the installation of grass underway.

8,000 m2 out of a total 20,000 m2 of grass has been placed, with the remainder set to be completed by the end of January. The project is on schedule to meet commitments for the upcoming football season.

Image Source: Wikimedia Commons